Root Crops (Carrots)

During Fall Land Preparation:
Apply 2 gallons per acre using required mineral nutrition. 

During Planting:
Apply 2 gallons per acre using irrigation system or side-dress method, along with required mineral nutrition. 

Before Bulking (approx. 30 days from planting):
Apply 2 gallons per acre using required mineral nutrition.

During First-phase of Fruit Development:
Apply 2 gallons per acre using required mineral nutrition.

About 45 days from planting: 
Apply 1 gal/acre using required mineral nutrition.

About 60 days from planting:
Apply 1.5 gal/acre using required mineral nutrition.